Text Box: SUMMARY

Commissioning services for a performance contract, from project audit phase through monitoring and verification for the entire complex. 

Size: 12 buildings, over 1 million square feet

Overall value: $16 million

Bridgewater (MA)

Correctional Facility

ADI reviewed and approved a $16 million project from the energy audit phase through the operations phase. The Massachusetts Division of Capital Asset Management (DCAM) requested that ADI commission all energy conservation measures and evaluate any pricing project changes that accrued over the term of the contract. Commissioning plans included pre-functional and functional tests.   

ADI also completed a detailed savings and costing analysis of all ECMs. These tests determined that the EMS needed to be further commissioned by the ESCO in order to provide the savings as stipulated.

UNIQUE VALUE TO CUSTOMER

2348 Post Road, Suite 21

Warwick, RI 02886

Phone: 401.524.5334

Fax: 877.727.3699

www.ad-institute.com

E-mail: info@ad-institute.com

www.ad-institute.com

Text Box: SERVICES

n Energy audit development and
analysis

n Energy savings analysis

n Commissioning

n Preparing/analyzing energy savings M&V reports

n EMS trending

n Energy modeling

Text Box: MEASURES

n Lighting

n HVAC upgrades

n EMS

n Water conservation I-Con system

n Steam traps

n Variable speed drives

n Boiler

n Cogeneration 

n Power factor correction

n Laundry Conservation measure